The following tests and inspections shall be made at the
place of manufacture prior to despatch; but in the event of
any of the material proving unsatisfactory in the course of
being worked into boilers, such material shall be rejected,
notwithstanding any previous certificate of satisfactory testing,
and such further tests of the material from the same charge
shall be made as the Inspecting Officer in attendance may
consider desirable.
|